There is no stopping the civils team at the moment - we have been buys getting through the summer maintenance list. We were down in Devon last week re-building a crane hardstanding for a major component change as well as planned civils maintenance on a...

We have been out on a lot of RES managed wind farms this week! New palisade gate installation in Ayrshire, Fire Risk Assessment in Lanarkshire and general site maintenance work in Aberdeenshire! Great to be getting through the ever growing list of jobs to do!...

We have been up in the bonnie Scottish Highlands recently carrying out foundation inspections for our client SSE Renewables - we have been working through their planned inspection regime across a number of sites in their on-shore wind portfolio this summer. #windenergy #assetmanagement #civilengineering #renewableenergy...

Its been a busy couple of weeks getting through the quarterly site inspections on our managed FiT wind portfolio for the Foresight Group and on the Osprey Charging Network sites. 31 wind sites and 30 EV charging sites visited over the course of June -...

The good weather has been ideal for getting on with our annual weed spraying campaign across a number of wind and solar assets across the UK! ...

We have been busy carrying out transformer exchanges over the past 2 weeks. We were instructed to design, procure, install and commission 2 x new transformers for 2 of our managed FiT wind sites in England for Foresight Group. Works completed safely and on time to...

We have been down in Wigton, Cumbria for the last few weeks constructing a new hardstanding and cable protection crossing point for a major component change on one of our clients RES managed wind farms. Wallace DS were appointed as Principal Contractor, Principal Designer and Designer for...

One of the Wallace DS civils teams are in Perthshire this week on a hydro scheme carrying out the annual intake clearing. Managed to catch the works during a break in our good old Scottish weather! ...

The Wallace team have been working on this gas peaking site in Edinburgh for the last 6 months. We have been supporting our client with procuring, constructing and the electrical fit out for a new secondary DNO building, backfilling and reinstating cable trenches and constructing...