Wallace DS acted as Client Technical Advisor for the construction phase of this 450kW hydro on the Allt a’choire Fhuadaraich within the Glenample Estate, Lochearnhead. With a gross head of 267m and a1.7km buried pipeline the scheme is anticipated to generate 1,290 MWh/Year and could power over 200 homes. The project was a challenging build due to the remote location, inclement weather, logistical constraints requiring helicopter utilisation and HSEQ due to COVID-19. The project is now fully commissioned and generating renewable energy to the local grid network.